Northwest Phase 4: During the week of March 15, 2026, the engineering team and subconsultants completed soil borings and test pits at the Northwest Phase 4 site. The team is working on the design for grading this area.
Airfield Equipment Storage Building: The subsurface exploration field work is complete. The design team is working towards their 60 percent design.
Worldwide Drive: The contractors are still in design phase working towards the 60 percent design.
Taxiway K Rehabilitation – Phase 1: The first phase of Taxiway K Rehabilitation has been bid and was awarded at the April Board meeting. The design team is working with the contractor to start this project in the coming months.