Taxiway D Reconstruction – Phase 1: The contractor finished the Delta 1 and 2 connectors and the paving of the mainline. The final marking will be done thirty days after the asphalt has been placed. The contractors will roll into phase 2, which will go to Taxiway H.

Triturator Project – The contractor is almost complete with this project and will be performing the training during the end of August.

Line-of-Sight Clearing Project – The contractor is wrapping up erosion control items and seeding. Due to the heavy rain, the contractor needs to repair some of the washing and rills that have occurred.